Project Update #11 - November 2023 - 2

  • ben6908
  • Nov 22, 2023
  • 1 min read

We have received concerns about recent noise on site stemming from a generator. We are waiting for Toronto Hydro to provide construction power to the site, which we were recently notified will now be delayed until mid-December. This is unfortunately out of our control.


The power is particularly necessary right now because during excavation we need to pump groundwater from the site. Without power, we are forced to run a generator to continue to pump groundwater from the property. However, an enclosure is being built around the generator which will hopefully help dampen the noise. We will continue to follow up with Toronto Hydro for an update on timing.

 
 
 

Recent Posts

Project Update #30 - January 2026

As part of the final stages of the watermain upgrade work on Montclair Avenue, the hydrants will be tested on January 7, 2026. The purpose of the tests is to confirm that the hydrants have sufficient

 
 
 

Comments


© 2023 Montclair Developments LP

bottom of page