top of page

Project Update #13 - January 2024

  • Jan 29, 2024
  • 1 min read

The staging slab along the west side of the site has been poured which allows for better truck circulation through the site.


Excavation continues and has reached the bottom of the pit in certain areas of the site.


We have started to pour footings which will support the structure of the building. Next, the crane base will be dug prior to crane erection in March 2024.


 
 
 

Recent Posts

Project Update #30 - January 2026

As part of the final stages of the watermain upgrade work on Montclair Avenue, the hydrants will be tested on January 7, 2026. The purpose of the tests is to confirm that the hydrants have sufficient

 
 
 

Comments


© 2023 Montclair Developments LP

bottom of page