Project Update #14 - February 2024

  • ben6908
  • Feb 23, 2024
  • 1 min read

We continue to excavate portions of the site for footings along the west side of the property.


During the week of February 26th, there will be multiple large concrete pours to form the footings and crane base. These pours may extend beyond normal working hours if needed.


We expect that the west crane will be installed in early to mid March, while we concurrently move east within the site to complete the remaining footings.

 
 
 

Recent Posts

Project Update #27 - May 2025

Construction work will resume on May 5th for infrastructure improvement on Montclair Avenue and Tweedsmuir Avenue. As part of this work,...

 
 
 
Project Update #26 - April 2025

The project has received an exemption permit to allow for the dropoff of material between the hours of 6:30am and 9pm. There may be...

 
 
 
Project Update #25 - January 2025

Toronto Hydro will commence work next week to install permanent power to the site. As part of their work, they are upgrading the...

 
 
 

Komentarze


© 2023 Montclair Developments LP

bottom of page