The west crane installation is tentatively scheduled for Tuesday March 5th. This date is weather dependent and may be pushed as needed.


On the crane installation day, the south portion of Montclair Avenue will be occupied to accomodate the crane delivery. Large flatbed trucks and other vehicles will be needed to facilitate the delivery. We expect that Montclair Ave will be occupied from approximately 7am to 7pm.

 
 
 

Recent Posts

Project Update #27 - May 2025

Construction work will resume on May 5th for infrastructure improvement on Montclair Avenue and Tweedsmuir Avenue. As part of this work,...

 
 
 
Project Update #26 - April 2025

The project has received an exemption permit to allow for the dropoff of material between the hours of 6:30am and 9pm. There may be...

 
 
 
Project Update #25 - January 2025

Toronto Hydro will commence work next week to install permanent power to the site. As part of their work, they are upgrading the...

 
 
 