Project Update #16 - March 2024

  • ben6908
  • Mar 6, 2024
  • 1 min read

The first crane was installed along the west side of the site on March 5th.


The next crane is scheduled to be installed on either March 13th or 14th, weather dependent. Similar to the first crane, portions of Montclair Avenue will be closed on the day of installation.


The third and final crane will likely be installed in early to mid April, but an update will be posted on this website closer to the installation date.

 
 
 