top of page

Project Update #23 - November 2024

  • ben6908
  • Nov 26, 2024
  • 1 min read

At the end of November through to the middle of December, we will be pouring a large transfer slab. This slab is thicker and more complicated than the typical floors in the building, and as a result, the duration to complete this floor will take longer than normal.


We have received a noise exemption permit from the City that permits work outside of normal working hours. These extended hours are necessary to complete daily pours that will extend into the night on occasion.

 
 
 

Recent Posts

Project Update #27 - May 2025

Construction work will resume on May 5th for infrastructure improvement on Montclair Avenue and Tweedsmuir Avenue. As part of this work,...

 
 
 
Project Update #26 - April 2025

The project has received an exemption permit to allow for the dropoff of material between the hours of 6:30am and 9pm. There may be...

 
 
 

Comments


© 2023 Montclair Developments LP

bottom of page