Project Update #23 - November 2024

  • ben6908
  • Nov 26, 2024
  • 1 min read

At the end of November through to the middle of December, we will be pouring a large transfer slab. This slab is thicker and more complicated than the typical floors in the building, and as a result, the duration to complete this floor will take longer than normal.


We have received a noise exemption permit from the City that permits work outside of normal working hours. These extended hours are necessary to complete daily pours that will extend into the night on occasion.

 
 
 

Recent Posts

Project Update #30 - January 2026

As part of the final stages of the watermain upgrade work on Montclair Avenue, the hydrants will be tested on January 7, 2026. The purpose of the tests is to confirm that the hydrants have sufficient

 
 
 